We appreciate your support and trust. We look forward to serving our community by improving our facilities and learning environments for our students, staff, teachers and community.
On February 9, 2016, the Bainbridge Island community approved a bond measure to replace Blakely Elementary School and the Bainbridge High School 100 Building. We take this responsibility seriously and are committed to being careful stewards of your investment.
Blakely Elementary Replacement Project
Project Timeline
| Feb. 2016 | Bainbridge Island voters approve the bond to replace Blakely Elementary. |
| Aug. 2016 | The Blakely Educational Specifications Report is completed. |
| Sept. 2019 | The new Blakely Elementary opens to students. |
Project Documents
Committee Members
| Board | Mev Hoberg |
|---|---|
| Administration | Sheryl Belt, Tamela Van Winkle, John Gray, Carrie Morgan |
| Blakely | Reese Ande, Teresa Ball, Terra Claiborne, Amanda Gardner, Kyanne Hawkins, Karen Keller, Karin Knight, Lisa McCassey, Kathleen Pool, Kathleen Watt, Maureen Wilson |
| Mithun | Brendan Connolly, Richard Franko, Susan Olmsted |
Blakely photos by Kevin Scott.
BHS 100 Building Replacement Project
The February 2016 bond funded replacement of the Bainbridge High School 100 Building. In February 2019, the community approved a levy to supplement the project and complete its full scope:
| ✓ Replacement of the BHS 100 Building |
| ✓ Remodel of the 200 Building commons into a theatre |
| ✓ Remodel of the 300 Building classrooms |
Project Timeline
| Feb. 2016 | Bainbridge Island voters approve the bond to replace the BHS 100 Building. |
| Sept. 2016 | A Steering Committee forms to select an architect and begin Educational Specifications. |
| 2017 | The committee and architect Mahlum explore concepts for CTE, performing arts and Special Education spaces. |
| 2018 | The committee reviews theatre options, site plans and cost comparisons, leading to the schematic design. |
| Feb. 2019 | Voters approve a levy to complete the full project scope, including the theatre and 300 Building remodels. |
| July 2019 | Construction documents reach 90% completion. |
Project Documents
→ BHS 100 Building Steering Committee Flow Chart
→ BHS 100 Building Update Presentation to the Board (May 2017)
→ Steering Committee Presentation (Feb. 15, 2018)
→ Steering Committee Meeting Minutes (March 14, 2018)
→ Steering Committee Presentation (April 18, 2018)
→ BHS 100 Building Update to School Board (April 26, 2018)
→ BHS 100 Building Replacement Update (Sept. 13, 2018)
→ BHS 100 Building Ed Specs, Schematic Design & Levy Conversation (Oct. 25, 2018)
→ BHS Schematic Design Presentation
→ BHS 100 Building Design Development & Cost Estimate (Feb. 28, 2019)
→ BHS 200 Building Theatre Remodel (March 26, 2019)
→ BHS 100 Building Inclusive Restroom Design (March 28, 2019)
→ BHS 100 Building Cost Conversation (May 31, 2019)
→ BHS 100 Building 90% Construction Documents with Value Engineering (July 25, 2019)
Steering Committee Members
| Board | Lynn Smith, Mike Spence |
|---|---|
| BHS Staff | Kristen Haizlip, Duane Fish |
| BISD Administration | Erin Murphy, Sheryl Belt |
| Community | John Ellis, Ian Forbes, Tom McCloskey, Bruce Weiland, Clint Pells |
| Capital Projects | Tamela Van Winkle, Carrie Morgan |
| CTE Advisors | Peggy Templeton, Sean Eaton |